Difference between revisions of "User:Daleharvey"

From Inkscape Wiki
Jump to navigation Jump to search
Line 1: Line 1:
<h2>OverView</h2>
<h2>Whiteboard</h2>
 
<p>I had intended on a working prototype at this point of the program, however an unexpected delay came up with a bug in server implementations which needs to be resolved</p>
 
<p>Throughout the time of summer of code I had expected to complete a release worthy implementation of the whiteboard extension, however as I am yet to recieve the first payment from the program. I had to spend a significant time that i had planned on using on the whiteboard project in finding a job and working to get the money I had budgeted to recieve from google, which has seriously affected my timeline.</p>
 
<p>Following is a Todo list of the tasks I have yet to do, and a timescale in which i plan to implement them</p>
 
<h2>TODO</h2>
<ol>
<li>Manually serialise incoming message - 2 days, 30th August</li>
<li>Apply incoming changes to the whiteboard - 5 days, 3rd September</li>
<li>Finalise and implement MUC session establishment - 6 days</li>
<li>I will give 2/3 weeks afterwards dedicated to making sure the whiteboard is release worthy</li>
</ol>
 
<p>Given this timescale I fully expect to have a release worthy implementation for October</p>

Revision as of 19:58, 15 August 2006

Whiteboard

I had intended on a working prototype at this point of the program, however an unexpected delay came up with a bug in server implementations which needs to be resolved

Throughout the time of summer of code I had expected to complete a release worthy implementation of the whiteboard extension, however as I am yet to recieve the first payment from the program. I had to spend a significant time that i had planned on using on the whiteboard project in finding a job and working to get the money I had budgeted to recieve from google, which has seriously affected my timeline.

Following is a Todo list of the tasks I have yet to do, and a timescale in which i plan to implement them

TODO

  1. Manually serialise incoming message - 2 days, 30th August
  2. Apply incoming changes to the whiteboard - 5 days, 3rd September
  3. Finalise and implement MUC session establishment - 6 days
  4. I will give 2/3 weeks afterwards dedicated to making sure the whiteboard is release worthy

Given this timescale I fully expect to have a release worthy implementation for October