Revision as of 11:45, 24 October 2020
Draft
Release Coordinators
- Developement: ?
- Translations: ?
- Vectors: ?
Required Features
- Comand Palette
- New dialog panels
Postponable Features
- ?
Critical Bugs
Release Notes
Release Announcement
- Link
Schedule
Milestone | Interval | Date | Fallback |
---|---|---|---|
Branch - Feature Freeze | - | November 29th | |
Alpha | 8 Weeks | January 24th | |
Beta - Hard Freeze | 4 Weeks | February 21st | |
Translation Freeze | NA | ? | |
Release Notes, etc. | NA | ? | |
Release Candidate 1 | 1 Week | March 7th | |
Release Announcement Ready | NA | ? | |
Release Candidate 2 (if needed) | 1 Week | March 14th | |
Populate Mirrors | 3 Days | March 17th | |
Release | March 20th |