Revision as of 11:45, 24 October 2020

Draft

Release Coordinators

  • Developement: ?
  • Translations: ?
  • Vectors: ?

Required Features

  • Comand Palette
  • New dialog panels

Postponable Features

  •  ?

Critical Bugs

Release Notes

Release Announcement

  • Link

Schedule

Milestone Interval Date Fallback
Branch - Feature Freeze - November 29th
Alpha 8 Weeks January 24th
Beta - Hard Freeze 4 Weeks February 21st
Translation Freeze NA ?
Release Notes, etc. NA ?
Release Candidate 1 1 Week March 7th
Release Announcement Ready NA ?
Release Candidate 2 (if needed) 1 Week March 14th
Populate Mirrors 3 Days March 17th
Release March 20th