Difference between revisions of "User:Daleharvey"

From Inkscape Wiki
Jump to navigation Jump to search
(tutorial documentation: very important! :-))
 
(29 intermediate revisions by one other user not shown)
Line 1: Line 1:
<h2>OverView</h2>
<h2>Whiteboard</h2>
I have decided to set up this page as my log for the google summer of
code project, formalising the protocol for inkboard communication
and converting the library to pedro.


<h2>Predicted TimeLine</h2>
<p>I had intended on a working prototype at this point of the program, however an unexpected delay came up with a bug in server implementations which needs to be resolved, I am about to go on a holiday until the 27th and will not be able to undertake any more development until this time</p>
 
<p>Throughout the time of summer of code I had expected to complete a release worthy implementation of the whiteboard extension, however as I am yet to recieve the first payment from the program. I had to spend a significant time that i had planned on using on the whiteboard project in finding a job and working to get the money I had budgeted to recieve from google, which has seriously affected my timeline.</p>
 
<p>Following is a Todo list of the tasks I have yet to do, and a timescale in which i plan to implement them</p>
 
<h3>TODO</h3>
<ol>
<li>Finalise manually serialising incoming message - 2 days, 30th August</li>
<li>Apply incoming changes to the whiteboard - 5 days, 4th September</li>
<li>Finalise and implement MUC session establishment - 6 days, 9th September</li>
<li>implement conflict resolution - 5 days,14 September</li>
<li>I will give 2 weeks afterwards dedicated to making sure the whiteboard is release worthy</li>
<li>Easy to follow step-by-step whiteboard tutorial documentation, specially how to use it on a GoogleTalk account (GoogleTalk is Jabber).</li>
</ol>
 
<p>Given this timescale I fully expect to have a release worthy implementation for October</p>
 
<h4>Progress</h4>
<ol>
<li>Serialising Incoming messages - done, jabber.org ensures the in-order processing</li>
 
<li>Apply Incoming Changes - 80% complete, need to handle special case nodes such as defs, and transformation matrices, plus ordering of objects</li>
 
<li>Conflict resolution - 90% complete, need to finalise rollbacks</li>
</ol>
 
<h3>Done</h3>
<ul>
<ul>
<li><h3>Deliverable 1 - Friday, 30th June</h3>
<li>State and Session Handling<li>
  <p>Extend and finalise the initial draft of the protocol specification started
<li>Peer to peer session establishment</li>
    by David Yip (/src/jabber_whiteboard/protocol/protocol.tex), intergrating as much of the standard protocol underdevelopment at http://wiki.jabber.org/index.php/Psi_Whiteboarding which must include the following</p>
<li>Whiteboard clients broadcast all changes to the document</li>
<ul><li>Specification for conflict resolution</li>
<li>Developed a formal protocol in liason with joonas of the psi project location : http://debrowse.com/whiteboard/wb.xml</li>
<li>Use Case for peer to peer and Multi User Chat session establishment</li>
<li>Use Case for communication of edits between sessions</li>
<li>Listing of valid message types</li>
<li>State transition diagram of Inkboard Clients</li>
</ul>
</li>
<li><h3>Deliverable 2 - Friday, 14th July</h3>
<p>Develop and finalise the XML schema that is implemented by the inkboard clients, this will define the valid message types that may be transferred</p>
</li>
<li>Deliverable 3 - Friday 28th July
<p>A basic inkboard client developed using the perdo XMPP client, must be stable enough to be integrated with the trunk, that contains at least the following<ul><li>Initialisation and Destruction of multi user and peer to peer session</li><li>Basic communication of changes between documents</li></ul></li>
<li>Final Deliverable - Monday 21th August
<p>End of Summer of Code project, a fully stable inkboard intergrated into the inkscape trunk, ready for inclusion in the release of .45, features to include:
<ul><li>Conflict Resolution</li><li>Local Undo mechanism</li></ul></p>
</li>
</ul>
</ul>


<h2>Project Log</h2>
<p>Sorry to all who expected the whiteboard to be working at a time before this, for the reasons given above I have been unable to stick the the original schedule. However I fully plan on sticking to the timescale given and finishing the whiteboard. And of course after the whiteboard is complete I fully intend to carry on working on its, or other aspects of inkscapes future development</p>
<em>21/06/05</em><br />
I have finished uni and can start working full time on the protocol / lib
conversion. We have decided to integrate the whiteboard gui into the pedro
gui. I am starting my work with adding the whiteboard gui into pedro, and
defining groupchat and peer to peer initialisation protocol

Latest revision as of 12:49, 12 June 2008

Whiteboard

I had intended on a working prototype at this point of the program, however an unexpected delay came up with a bug in server implementations which needs to be resolved, I am about to go on a holiday until the 27th and will not be able to undertake any more development until this time

Throughout the time of summer of code I had expected to complete a release worthy implementation of the whiteboard extension, however as I am yet to recieve the first payment from the program. I had to spend a significant time that i had planned on using on the whiteboard project in finding a job and working to get the money I had budgeted to recieve from google, which has seriously affected my timeline.

Following is a Todo list of the tasks I have yet to do, and a timescale in which i plan to implement them

TODO

  1. Finalise manually serialising incoming message - 2 days, 30th August
  2. Apply incoming changes to the whiteboard - 5 days, 4th September
  3. Finalise and implement MUC session establishment - 6 days, 9th September
  4. implement conflict resolution - 5 days,14 September
  5. I will give 2 weeks afterwards dedicated to making sure the whiteboard is release worthy
  6. Easy to follow step-by-step whiteboard tutorial documentation, specially how to use it on a GoogleTalk account (GoogleTalk is Jabber).

Given this timescale I fully expect to have a release worthy implementation for October

Progress

  1. Serialising Incoming messages - done, jabber.org ensures the in-order processing
  2. Apply Incoming Changes - 80% complete, need to handle special case nodes such as defs, and transformation matrices, plus ordering of objects
  3. Conflict resolution - 90% complete, need to finalise rollbacks

Done

  • State and Session Handling
  • Peer to peer session establishment
  • Whiteboard clients broadcast all changes to the document
  • Developed a formal protocol in liason with joonas of the psi project location : http://debrowse.com/whiteboard/wb.xml

Sorry to all who expected the whiteboard to be working at a time before this, for the reasons given above I have been unable to stick the the original schedule. However I fully plan on sticking to the timescale given and finishing the whiteboard. And of course after the whiteboard is complete I fully intend to carry on working on its, or other aspects of inkscapes future development